mini placer
PourItOut 09-26-2013
comment profile send pm notify


PourItOut 09-26-2013
reply profile send pm notify


PourItOut 09-26-2013
reply profile send pm notify


PourItOut 09-26-2013
reply profile send pm notify


PourItOut 09-26-2013
reply profile send pm notify


PourItOut 09-26-2013
reply profile send pm notify


PourItOut 09-26-2013
reply profile send pm notify


PourItOut 09-26-2013
reply profile send pm notify


Many 09-27-2013
reply profile send pm notify

that gives me a headache Cool


PourItOut 09-27-2013
reply profile send pm notify

gave me a headach trying to post them in the right order, lol


Dipstick 09-27-2013
reply profile send pm notify

I don't realy get it.. All this trouble and costs while there is a tower crane right there.. Why not take that wall with crane and bucket??


PourItOut 09-27-2013
reply profile send pm notify

They told me that a crane and bucket was not approved by the GC, it is actually faster to pour this way, pipeline and placer can stay connected for several days, only having to add pipe as we go, only thing bucket was used for was to blow system clean


PourItOut 09-27-2013
reply profile send pm notify


Boomerr 09-27-2013
reply profile send pm notify

A good reason for an oiler on this job, I could think of some easier ways of doing it. I bet they think it is just great.  LOL


dlee7729 10-02-2013
reply profile send pm notify

The GC didn't want to tie his tower crane up on a hours long bucket pour while the other trades stand around waiting for a lift.


dlee7729 10-02-2013
reply profile send pm notify

And I am sure the crane opertor has a oiler. He is easy to spot . The dress jeans and 100 buck class 3 pull over.