MY LINE PUMP JOB (Now 20th Floor Total 44th Floor)
Munir 05-14-2008
comment profile send pm notify

http://www

 


sccp jamie 05-14-2008
reply profile send pm notify

wow! sod leaving your sandwich box down the bottom lol


Bob 05-14-2008
reply profile send pm notify

Those pics bring back some memories.

No shutoff or diversion valves. No placing booms.

Pump - Pipe - Hose                            

and Pour it out

Life was more simple then ;~)


Munir 05-14-2008
reply profile send pm notify

Mr. Bop

Yes you are right.                                 We have inside building more length of pipe line but I can’t make picture.   After 25th floor we will use shutoff valve.                                        Contractor is no hire placing boom because each floor is only 105m3 they are using tower crane.                    Thank you.  

                              

 

 


ruck 05-14-2008
reply profile send pm notify

Munir

Great pics, Any luck with jobs.

Ruck